Knock down rebuild: the hidden site costs and how to check your block first

The hidden costs in a knock down rebuild mostly come from the block, not the house. A builder's base price assumes a fairly flat, easy site. Slope, flood levels, bushfire rating, sewer and stormwater pipes, easements, heritage or character controls on demolition and reactive clay are the things that move the final price, and every one of them can be checked from public mapping before you sign a building contract.

You already own the land, so this is not about whether to buy. It is about knowing what your block brings to the build before the builder's site inspection, so the site costs in the tender are not a surprise.

What are site costs in a knock down rebuild?

Site costs are the part of a build price that depends on the land rather than the house design. Builders usually price them separately from the base house, either as an allowance in the first quote or as a fixed figure after a site inspection, a survey and a soil test. They cover things like earthworks to make a level pad, retaining walls, extra footing depth, connecting sewer and stormwater, and meeting the construction rules for flood or bushfire.

Two blocks in the same street can carry very different site costs for the same house. That is why the block is worth checking first.

The block checks that change the price

What to check Why it changes the build Where it is mapped
Slope and fall A sloping block needs cut and fill, retaining walls or a split-level design. The direction of fall decides whether stormwater can drain to the street. Government elevation data (contours)
Flood A flood overlay can set a minimum floor level, which can lift the slab or the whole house. Council flood overlays and flood studies
Bushfire A bushfire prone lot needs a Bushfire Attack Level (BAL) assessment, and a higher BAL means tougher construction rules for walls, windows and roofing. State bush fire prone land maps
Sewer and stormwater pipes Building over or close to a main usually needs the water authority's approval, and can push the house footprint away from the pipe. Water authority and council infrastructure maps
Easements You usually cannot build a permanent structure over a drainage or sewer easement, so it can shrink the buildable area. Registered easements on the cadastre and title
Heritage and character A heritage listing or a character overlay can stop the old house being demolished without approval. Council planning scheme overlays and heritage registers
Soil reactivity Reactive clay shrinks as it dries and swells as it wets, so the footings and slab have to be designed for it. Geological mapping and nearby bore logs (indicative only)

Slope and which way the block falls

A builder's standard price usually allows only a small fall across the house footprint. Past that, a slab needs cut and fill and often retaining walls, or the design changes to a split level or a suspended floor. The fall direction matters as much as the amount: a block that falls away from the street may not be able to drain stormwater to the kerb by gravity, which can mean an easement through a downhill neighbour or a pump.

Contours and cross sections from government elevation data show how much the block falls and which way before anyone visits. They are not a survey. The surveyor's contour plan replaces them before the design is finalised.

Flood levels and floor heights

If any part of the lot is in a flood overlay, the council can set a minimum habitable floor level for the new house, usually a set height above a modelled flood level. On a low block this can lift the slab, add steps and ramps, or change the design to a raised floor. Some councils publish a flood report or flood level for the property. Ask the council for the flood level that applies before the designer draws the floor.

In NSW, flood planning controls also change which approval path is open. A flood control lot can still use complying development, but extra standards apply (State Environmental Planning Policy (Exempt and Complying Development Codes) 2008).

Bushfire rating (BAL)

On bush fire prone land, a new house needs a Bushfire Attack Level assessment. The BAL sets the construction standard under AS 3959: the higher the level, the stricter the rules for glazing, cladding, decking, roofing and gutters. In NSW, land rated BAL-40 or the flame zone (BAL-FZ) cannot use complying development for a new house, so the rebuild goes through a development application instead (Codes SEPP cl 1.19A).

The state map shows whether the lot is bush fire prone. It does not give the BAL. That comes from a bushfire assessment of the site, so ask for it early if the lot is mapped.

Sewer and stormwater pipes near the house

Many older suburbs have a sewer main running across the back of the lots. A new house is often larger than the old one and can reach the pipe. Building over or next to a water authority's main usually needs its approval and can add design conditions, such as deeper footings near the pipe or keeping a clear strip above it. In Sydney, plans go through Sydney Water's building plan approval, and it refers plans that build over or next to its assets for review (Sydney Water, Building over and adjacent to assets policy).

Stormwater has to leave the site at a lawful point of discharge, usually the kerb or a council pipe. The fall of the block and where the council's pipes run decide how easy that is.

Easements on the title

An easement gives a council, water authority or neighbour a right over part of your land. Drainage and sewer easements generally cannot be built over, so on a narrow lot an easement down one side can change the house you can fit. Easements are registered on the title and drawn on the survey plan. Mapped easement lines on the cadastre help you see them early, but the title is the authority. See easements explained for the common types.

Heritage and character controls on demolition

A knock down rebuild starts with the knock down, and some houses cannot be demolished without approval. A house listed as a heritage item cannot be demolished as complying development in NSW, and land in a heritage conservation area is excluded from the Housing Code, so a new house there goes through a development application (Codes SEPP cl 1.19(1)(a)). In Brisbane, houses built in 1946 or earlier inside the Traditional building character overlay need council approval to demolish, and the council can refuse it.

Check the planning scheme overlays for the lot before you sign with a builder. If one applies, the timeline and the design both change.

Soil reactivity

Reactive clay shrinks as it dries and swells as it wets, and the slab and footings are designed for how much the ground is expected to move. The soil test the builder orders gives the site class under AS 2870, and that class sets the footing design. Highly reactive clay, or a site with fill or trees nearby, usually means a stiffer and deeper slab.

Geological mapping and nearby bore logs give an indicative reactivity range before the soil test. They do not replace it: the site investigation decides the class.

Approval path: complying development or a DA?

In NSW, a new single house can often be approved as complying development under the Housing Code, which is faster than a development application. The same mapped constraints above decide whether that path is open: heritage, a heritage conservation area, Class 1 or 2 acid sulfate soils, coastal hazards, BAL-40 or flame zone and some environmental overlays all exclude it (Codes SEPP cl 1.19 and 1.19A). In Queensland the planning scheme overlays decide whether the new house needs a planning approval or only a building approval.

What to ask the builder

Take the block facts to the first meeting and ask:

  • What fall does your base price allow for, and what happens to the price if my block falls more than that?
  • Is the slab priced for the soil class, or is that a provisional allowance until the soil test?
  • Who arranges the BAL assessment and the flood level, and is the construction for them included?
  • Is there a sewer main within reach of the new footprint, and who applies for build-over approval?
  • Where will stormwater discharge, and is any pump, easement or pipe work included?
  • Which approval path are you assuming (complying development, a DA or building approval only), and what happens if the house needs a DA?
  • What is in the demolition price: disconnections, asbestos removal and tree removal?

Checking the block before the builder's site visit

LayeredGeo's $9 Property Report maps the zone, flood, bushfire, heritage and character overlays, registered easements and the water, sewer and stormwater pipes for one address, with the share of the lot each overlay covers. Adding the Terrain Report ($18 for both) shows the contours, cross sections with the grade, and which way water flows across the block. Where a published flood model covers the address, the Flood Model Report adds modelled flood depths and levels. The $119 geotechnical desktop study gives an indicative soil reactivity range from mapped geology and nearby bore logs in QLD, NSW, VIC and SA.

None of these is a survey, a soil test or a cost estimate. They give you the facts about the block to take to the builder, so you can ask the right questions before the site costs are priced.

Common questions

What are the hidden costs of a knock down rebuild?

Most hidden costs come from the block rather than the house: slope and retaining, a minimum flood floor level, the bushfire construction level (BAL), building near a sewer main, easements, approval to demolish under heritage or character controls, and footings for reactive clay. Each can be checked from public mapping before you sign a building contract.

Can I knock down and rebuild on a sloping block?

Yes, but a builder's base price usually allows only a small fall across the house. More fall means cut and fill, retaining walls or a split-level design, and a block that falls away from the street may need an easement or a pump to drain stormwater.

Do I need council approval to knock down my house?

Often yes. In NSW a house on land that is a heritage item or in a heritage conservation area cannot be replaced as complying development under the Housing Code, so it needs a development application. In Brisbane, houses built in 1946 or earlier in the Traditional building character overlay need council approval to demolish.

Can I build over a sewer pipe?

Usually only with the water authority's approval. Building over or next to a sewer main needs a build-over or building plan approval, and the authority can set conditions such as deeper footings or a clear strip above the pipe.

Before the builder's site visit

What your block brings to the build

Flood, bushfire, heritage and character overlays, registered easements and the sewer and stormwater pipes for your lot, with the Terrain Report's contours and fall for $18 together. The map preview is free.

Check your block → See a sample report

About this article. Published by LayeredGeo and written from the published research cited in the Sources section above. It is general information about how property and ground conditions are assessed in Australia, not engineering, planning, legal or financial advice, and it is not specific to any property. Check anything that matters against the source dataset or a suitably qualified professional before you rely on it. If you spot something wrong, tell us at hello@layeredgeo.com.au and we will fix it.